fandi
Senior Member
- Location
- Los Angeles
- Occupation
- Electrical Engineer
Hi All,
Currently no new loads added for each unit. But if the main service is being replaced MEANING THE EXISTING CONDITION IS BEING ALTERED, does the latest/current code (which is NEC 2014 in California) 225.39(D) kick in? And if the feeder breakers were 60A, then I guess the current 30A feeders have to be upsized to 60A rating also.
Thanks.
Currently no new loads added for each unit. But if the main service is being replaced MEANING THE EXISTING CONDITION IS BEING ALTERED, does the latest/current code (which is NEC 2014 in California) 225.39(D) kick in? And if the feeder breakers were 60A, then I guess the current 30A feeders have to be upsized to 60A rating also.
Thanks.