Designing a project with a existing 240-3 open delta service that we are upgrading. They are building a 3rd of the project now, and the other 2/3 at a future date.
My question is, we currently wont have any 3 phase loads, however we will in the future . Is it OK to bring the wild B leg in for future and use it for the service even if it wont be used now. Should I be worried about a balancing issue? What if we dont end up putting 3 phase loads in? I would like to have the 3 phase to keep the service size down.
Thanks
My question is, we currently wont have any 3 phase loads, however we will in the future . Is it OK to bring the wild B leg in for future and use it for the service even if it wont be used now. Should I be worried about a balancing issue? What if we dont end up putting 3 phase loads in? I would like to have the 3 phase to keep the service size down.