ceb58
Senior Member
- Location
- Raeford, NC
We have contractors installing some generators for us at work. These systems are being installed as SDS (switching the neutral in the ATS). The inspector is allowing the bonding of the neutral and GEC (from underground halo system) in the fusible disconnect at the building instead of at the breaker on the gen.
My question is after reading 250.30 A and getting a headache. They are bonding the frame of the gen. to the underground halo system but should there also be a system bonding jumper ran back from the disco. and bond to the frame of the gen. also?
My question is after reading 250.30 A and getting a headache. They are bonding the frame of the gen. to the underground halo system but should there also be a system bonding jumper ran back from the disco. and bond to the frame of the gen. also?