AJBelectric
Member
- Location
- Westchester, NY
Hi All,
New to to the forum so bare with me if this question has been addressed in some form.
I have recently been asked to complete a 277/480v 3phase 225a service. The service is fed
from a 400a MDP approximately 1500' away from the new panel location. I am picking up where the previous electric a contractor left off- he pulled 4 conductors to the location thinking that the service requirement was only single phase. Conductors are sized properly to account for voltage drop.
My question is: Can I wire the panel with 3 hot legs and a ground, and no neutral? All loads from this panel will be 3-phase equipment that won't require a neutral. And if a step-down 120/208 transformer is needed down the road, I should be able to feed it with 480v and a ground. Pulling in an additional conductor is not an option.
I have asked all my local inspectors but each seem to have a different opinion and no definitive solutions.
Any feedback is appreciated. Sorry for the long-winded post.
AJ
New to to the forum so bare with me if this question has been addressed in some form.
I have recently been asked to complete a 277/480v 3phase 225a service. The service is fed
from a 400a MDP approximately 1500' away from the new panel location. I am picking up where the previous electric a contractor left off- he pulled 4 conductors to the location thinking that the service requirement was only single phase. Conductors are sized properly to account for voltage drop.
My question is: Can I wire the panel with 3 hot legs and a ground, and no neutral? All loads from this panel will be 3-phase equipment that won't require a neutral. And if a step-down 120/208 transformer is needed down the road, I should be able to feed it with 480v and a ground. Pulling in an additional conductor is not an option.
I have asked all my local inspectors but each seem to have a different opinion and no definitive solutions.
Any feedback is appreciated. Sorry for the long-winded post.
AJ