Hello,
I am looking to install several battery systems on a 600a delta high leg 3 phase service. This means this service has 120/240 with a 208v high leg.
The panels within this site I am looking to back up are only 120/240 and do not contain the high leg, they are not 3 phase(although there are 3 phase panels on site).
My initial thinking is to install several individual residential 120/240 systems and a battery or 2 to each panel.
My concerns are that these systems are designed for a proper 120/240 single or split phase service.
Would there be issues with tying them into this service? Each of these panels that will be backed up have 3 wires and a ground-120/240, they each get 2 phase conductors from 2 of the 3 phases in this building's service.
Is this truly the same as a split phase 120/240? I would think that those 2 phases are 120 degrees out of sync(being from a 3 phase service) where a standard split phase has 2 conductors 180 degrees out of sync.
There will also be solar on site here(say several powerwalls with mods and MCI's on the roof)I am worried that powerwall(or any resi ESS system) will not output PV with the correct sine wave configuration.
So far I have reached out to several manufacturers trying to find a solution, the response I've gotten from each so far has been something along the lines of "this should work" or "this could work"
Has anyone done this with success?
Thank you
I am looking to install several battery systems on a 600a delta high leg 3 phase service. This means this service has 120/240 with a 208v high leg.
The panels within this site I am looking to back up are only 120/240 and do not contain the high leg, they are not 3 phase(although there are 3 phase panels on site).
My initial thinking is to install several individual residential 120/240 systems and a battery or 2 to each panel.
My concerns are that these systems are designed for a proper 120/240 single or split phase service.
Would there be issues with tying them into this service? Each of these panels that will be backed up have 3 wires and a ground-120/240, they each get 2 phase conductors from 2 of the 3 phases in this building's service.
Is this truly the same as a split phase 120/240? I would think that those 2 phases are 120 degrees out of sync(being from a 3 phase service) where a standard split phase has 2 conductors 180 degrees out of sync.
There will also be solar on site here(say several powerwalls with mods and MCI's on the roof)I am worried that powerwall(or any resi ESS system) will not output PV with the correct sine wave configuration.
So far I have reached out to several manufacturers trying to find a solution, the response I've gotten from each so far has been something along the lines of "this should work" or "this could work"
Has anyone done this with success?
Thank you