Alright. I know you all hate to just give answers and would rather give Articles. Unfortunately, I don't find anything relative to this particular installation. And, I think my math is way off. At least I hope it is. I am new to 3 phase calcs.
The installation is as follows:
2 - 40kw PDUs (480V input protected by 80A breaker)
1 - Fire suppression system (120V w/ 20A breaker)
1 - ten ton mini split AC system (don't have elec. requirements yet)
The data center is approx. 200' from the service.
I need help with sizing the disconnect and feeders. Any help is greatly appreciated.
Alright. I know you all hate to just give answers and would rather give Articles. Unfortunately, I don't find anything relative to this particular installation. And, I think my math is way off. At least I hope it is. I am new to 3 phase calcs.
The installation is as follows:
2 - 40kw PDUs (480V input protected by 80A breaker)
1 - Fire suppression system (120V w/ 20A breaker)
1 - ten ton mini split AC system (don't have elec. requirements yet)
The data center is approx. 200' from the service.
I need help with sizing the disconnect and feeders. Any help is greatly appreciated.