inspector 102
Senior Member
- Location
- Northern Indiana
Existing 600 amp service fed from pad mount transformer through 4" conduits into existing building to 600 MDP. Utility company wants a second meter installed to break out lighting loads for different tariff on billing. Contractor want to pull #2 conductor in with the existing conductors, through the 600 MDP, then out the building to a CT cabinet, then back into the building to a new 100 Amp Lighting panelboard. Sounds like there might be some code issues with coming into the building with service entrance conductors then going outside to metering, then back in. Also concerned about both sets of service entrance conductors in same conduit. Where should I be looking for specifics on this situation?