allenwayne
Senior Member
This is the senario,300 ft from mdp is a undrground feed to a guest cottage.For some reason unknown to me they only ran 3 # 2 al conductors.
The panel is in the kitchen of all places and the clearance is is encroached by counter space,the request was to hook up a package unit a/c.
I was considering bringing the 4 lighting circuits into a 6x6x4 pvc j box out side the building and nippling into a wp breaker box using the 6x6 as a way to extend the circuits into the new panel There is no ground per say and I will sink 2 ground rods ( the area is all sugar sand)The wp panel will have a main breaker so that there is a means of disconnect.
The reason for this is thst a package unit will be replacing one that I wish I had a pic of how it was installed. The panel is within sight of the unit so there goes the disconnect the water heater is inside and I told the customer that I will have to add a disconnect for it.There are only four circuits in the cottage,who ever wired it did install 2 appliance circuits but no gfci devices also told h/o they will be required the 2 remaiing circuits feed bath room l/r and bed room and dining area.Luckily ther dining is on the kistchen circuit so that is a no brainer .I asume I will have to add an afci to the remaining circuit to cover the bed room.I can eliminate the bath from the l/r quite easily and re feed off thel/r from the bedroom afci.
So there wil be 2 SA circuits one feeding the dining area the bath will be seperate and the l/r and bed room will cover the afci issue.
My only problem is that there is wil be a main disconnect at the cottage and since there is only a 3 wire feed from the mdp that the ground rods at the cottage will be okay to satisfy 250
The panel is in the kitchen of all places and the clearance is is encroached by counter space,the request was to hook up a package unit a/c.
I was considering bringing the 4 lighting circuits into a 6x6x4 pvc j box out side the building and nippling into a wp breaker box using the 6x6 as a way to extend the circuits into the new panel There is no ground per say and I will sink 2 ground rods ( the area is all sugar sand)The wp panel will have a main breaker so that there is a means of disconnect.
The reason for this is thst a package unit will be replacing one that I wish I had a pic of how it was installed. The panel is within sight of the unit so there goes the disconnect the water heater is inside and I told the customer that I will have to add a disconnect for it.There are only four circuits in the cottage,who ever wired it did install 2 appliance circuits but no gfci devices also told h/o they will be required the 2 remaiing circuits feed bath room l/r and bed room and dining area.Luckily ther dining is on the kistchen circuit so that is a no brainer .I asume I will have to add an afci to the remaining circuit to cover the bed room.I can eliminate the bath from the l/r quite easily and re feed off thel/r from the bedroom afci.
So there wil be 2 SA circuits one feeding the dining area the bath will be seperate and the l/r and bed room will cover the afci issue.
My only problem is that there is wil be a main disconnect at the cottage and since there is only a 3 wire feed from the mdp that the ground rods at the cottage will be okay to satisfy 250