1) I have a 30 kw single phase generator on a pad/structure remote from the house for emergency use only. I believe is a non-sds
2) 230.35 B seems to tell me I need a equipment bonding jumper between the gen disconnect and the ATS
3) My ATS will have a 3 wire from meter,4 wires from my panel and 4 wires from gen.
Question 1) Seems to me I need to have 4 wires (2 ungrounded, 1 grounded and 1 ebj) based on 230.35 B. Correct ?
Question 2) If so the neutral and ebj connect together in the ATS? Seems redundant, what am I missing here?
2) 230.35 B seems to tell me I need a equipment bonding jumper between the gen disconnect and the ATS
3) My ATS will have a 3 wire from meter,4 wires from my panel and 4 wires from gen.
Question 1) Seems to me I need to have 4 wires (2 ungrounded, 1 grounded and 1 ebj) based on 230.35 B. Correct ?
Question 2) If so the neutral and ebj connect together in the ATS? Seems redundant, what am I missing here?