RD35
Senior Member
- Location
- Bloomington, Indiana
Currently working on a design for a small RV park. Owner is a not-for-profit. They are trying to keep costs as low as possible. There will be a long (300ft+) feeder run that needs to be buried and comprised of parallel conductors. I could, conceivably, do this run as direct burial with URD aluminum cable runs. However, for the parallel DB cable runs to not be subject to derating, the subject code rule states that "spacing" must be maintained throughout the run. Can anyone tell me what "spacing" is required for a design of this type? Would, say, installing the runs side-by-side with a minimum of 2" of clean soil between the runs suffice in the bottom of a 24" deep trench?
Just for the sake of my own integrity, I plan to propose doing this install with conduit. But I want to be sure I give the owner all legal options.
Thoughts? OBTW this project is in Indiana and subject to the 2008 NEC.
Just for the sake of my own integrity, I plan to propose doing this install with conduit. But I want to be sure I give the owner all legal options.
Thoughts? OBTW this project is in Indiana and subject to the 2008 NEC.