Sparky Adam
Master Electrician
- Location
- Dallas, TX
- Occupation
- Operations Manager / Master Electrician
Here's a good one:
Standard single phase 320a meter base fed underground. Municipality wants the disconnect to contain the SBJ.
Two 200a main breaker cans as emergency service disconnects on each side of the meter can, each feeding a 200a sub panel inside.
Municipality requires a Ufer with #4 as GEC as well as a supplemental ground rod with a #6.
Question: which disconnect would the GEC go to?
Standard single phase 320a meter base fed underground. Municipality wants the disconnect to contain the SBJ.
Two 200a main breaker cans as emergency service disconnects on each side of the meter can, each feeding a 200a sub panel inside.
Municipality requires a Ufer with #4 as GEC as well as a supplemental ground rod with a #6.
Question: which disconnect would the GEC go to?