Customer installed a 37kw 240v 1ph insta heat in the mechanical room which is also where the service comes in.
It is a 400 amp service with (2) 200 amp 42 circuit loadcenters.
The unit requires (4) 40 amp 240v feeds to run it.
My question is, instead of taxing all of the load from (1) of the panels, would there be any issue of taking (2) feeds from each panel instead of all (4) from (1) ?
Would not be my 1st choice but its a heavy load regardless of where it comes from.