Hello. I know there are many variables. But generally speaking.
have 4- 4" conduit in trench that are being concrete encased( by others). point to point footage is 5,000'
Being able to get truck right up to where your laying conduits and assuming the trench is opened and available for conduits and very few offsets/bends. I'd assume you would use prefab elbows and not bend.
Do you think you think 2 guys could get a 80-100' in a 7 hour day?
have 4- 4" conduit in trench that are being concrete encased( by others). point to point footage is 5,000'
Being able to get truck right up to where your laying conduits and assuming the trench is opened and available for conduits and very few offsets/bends. I'd assume you would use prefab elbows and not bend.
Do you think you think 2 guys could get a 80-100' in a 7 hour day?