Tommy Hobbs
Member
I would like to have someone's opinon on this setup
(1) 120/208v 3ph 4w Electrical System
(2) 400A Breaker in 1200A Sub Panel in Main Electrical Room with Dual Load Lugs
(3) 200A M.L.O. Panel at North End of Plant Fed from above 400A Breaker
(4) 200A M.L.O. Panel at South End of Plant Fed from above 400A Breaker
(5) Feeder Sizes from 400A Breaker to each of the above 200A Panels is 350KCM THHN in to a wireway beneath each of the above Panels, Tapped off 350KCM with 3/0 THHN to Panels
Thanks for any replies,
(1) 120/208v 3ph 4w Electrical System
(2) 400A Breaker in 1200A Sub Panel in Main Electrical Room with Dual Load Lugs
(3) 200A M.L.O. Panel at North End of Plant Fed from above 400A Breaker
(4) 200A M.L.O. Panel at South End of Plant Fed from above 400A Breaker
(5) Feeder Sizes from 400A Breaker to each of the above 200A Panels is 350KCM THHN in to a wireway beneath each of the above Panels, Tapped off 350KCM with 3/0 THHN to Panels
Thanks for any replies,