ACL
Member
- Location
- Baltimore MD
I'm currently working on a renovation where the home has a 100A 2-phase service(single breaker main) feeding an old 100A F.Pacific panel and a 60A sub-panel in the basement. The homeowner wants to bring in a new 400A service to power (2) 200A panels. One panel would be located in the garage and the other in the center of the house on the 1st floor. What is the correct way to split the feed after the meter so that I can power both panels? My thoughts are to run from the meter, to a disconnect, then to a junction box where I would split the feed to run to each panel.