mshields
Senior Member
- Location
- Boston, MA
Would be very interested in your collective opinion on this:
I am replacing a 47 year old indoor unit substation with a new outdoor pad mounted transformer AND new indoor main switchboard albeit in a different location for a 90,000 square foot, 4 story college dormitory. So in a not entirely atypical fashion, we will install the new switchboard, run new conduit to the old switchboard. When everything is ready to go with the new, the contractor will de-energize and gut the old switchboard leaving the shell as a junction point.
Now here's my question. I have two options at that point. 1. pull all of the feeders some of which must run hundreds of feet to the various panelboards in this facility and replace them with new in the same conduits OR 2. Splice new conductors to these 47 year old circuits within the shell of the old switchboard.
On the one hand, I am terrified at the unknown factor of directing the contractor to pull these out. What if there is rusting of the conduit and they're stuck. What if he damages them in the process and then we need to run an entirely new feeder and because of the construction, the new feeder would have to be exposed making the people in charge of the dormitories very unhappy.
I lean towards leaving the 47 year old conductors. Do you agree that this is the best of my two options here?
Thanks,
Mike
I am replacing a 47 year old indoor unit substation with a new outdoor pad mounted transformer AND new indoor main switchboard albeit in a different location for a 90,000 square foot, 4 story college dormitory. So in a not entirely atypical fashion, we will install the new switchboard, run new conduit to the old switchboard. When everything is ready to go with the new, the contractor will de-energize and gut the old switchboard leaving the shell as a junction point.
Now here's my question. I have two options at that point. 1. pull all of the feeders some of which must run hundreds of feet to the various panelboards in this facility and replace them with new in the same conduits OR 2. Splice new conductors to these 47 year old circuits within the shell of the old switchboard.
On the one hand, I am terrified at the unknown factor of directing the contractor to pull these out. What if there is rusting of the conduit and they're stuck. What if he damages them in the process and then we need to run an entirely new feeder and because of the construction, the new feeder would have to be exposed making the people in charge of the dormitories very unhappy.
I lean towards leaving the 47 year old conductors. Do you agree that this is the best of my two options here?
Thanks,
Mike