A client recently had a conductor short to ground on a 3 phase supply to a transformer. It is supplying 480/277 to 120/208 3 phase 75kva transformer. There are no 3 phase loads but there are 208v electric heaters and 120v receptacles for general use power. Unfortunately where this is located it will be a couple of weeks before the repair can take place. I'm trying to think of a way to get some sort of temporary power restored until I can repair the conduit and pull wire. Does anyone have experience on phase loss on the primary of a transformer, and what can I expect to see?