MRUGEN SHETH
Member
I have to provide 6 welding receptacles of 480 volts, 3 phase, 60 amps fed from PDP. Out of these 2 are considering spare/future provision. Each receptacle shall be fed by individual feeder.
I do not have the information how these receptacles shall be loaded i.e one at a time or all at a time. NEC 630 provides the information for sizing of cables and OCPD.
How do I consider the loading effect (in KVA) to determine the PDP main breaker size feeding all these receptacles (i.e spare + Inservice)
Thanks.
I do not have the information how these receptacles shall be loaded i.e one at a time or all at a time. NEC 630 provides the information for sizing of cables and OCPD.
How do I consider the loading effect (in KVA) to determine the PDP main breaker size feeding all these receptacles (i.e spare + Inservice)
Thanks.