Some times it just get's lost in the translation. These are actual notes that I took off a set of plans:

1. The existing electrical system is to remain in the new addition space, not new equipment is reqts. for this area.
2. The inspector will be verify conform the plans, the electrical system on the field.
3. Two existing electrical single circuit from panel "A" w/breaker #15 will be used for the tortillas oven see floor plan sheet A-1.
4. The existing electrical services 200 amps. The inspector must be verify on the field the services electrical.
 
cowboyjwc said:
Some times it just get's lost in the translation. These are actual notes that I took off a set of plans:

1. The existing electrical system is to remain in the new addition space, not new equipment is reqts. for this area.
2. The inspector will be verify conform the plans, the electrical system on the field.
3. Two existing electrical single circuit from panel "A" w/breaker #15 will be used for the tortillas oven see floor plan sheet A-1.
4. The existing electrical services 200 amps. The inspector must be verify on the field the services electrical.

It's all Spanglish to me:D Y'all better learn it!
 
cowboyjwc said:
Some times it just get's lost in the translation. These are actual notes that I took off a set of plans:

1. The existing electrical system is to remain in the new addition space, not new equipment is reqts. for this area.
2. The inspector will be verify conform the plans, the electrical system on the field.
3. Two existing electrical single circuit from panel "A" w/breaker #15 will be used for the tortillas oven see floor plan sheet A-1.
4. The existing electrical services 200 amps. The inspector must be verify on the field the services electrical.
Hey, where'd you get my drawings?!?:grin: ;)
Seriously, it's mistakes like that that make my mistakes look less horrible.:cool:
 