I'm working with a subcontractor that swears his buried 4x70mm2 cu XLPE/SWA/PVC is good for a projected load of 250 Amps per phase. According to Table 310.16 of 2005 NEC the max ampacity for 70mm2 or about 1/0 cu before corrections is 170 Amps. Am I missing something or is 4x70mm2 cu XLPE/SWA/PVC unacceptable for this load?