Jps1006
Member
- Location
- Northern IL
We have a 400-amp 208 overhead service to replace. I tend to see most 400-amp services done in 500kcmil with 3 or 3-1/2 pipe. I don't see a lot of 400-amp services done with parallel 3/0. What are most of you doing? 500cu is over $6/ft and 3/0 is well under $3/ft. I hate trying to man-handle 500 especially in cool weather. Why do I see so many 400- amp services done in 500? Is it just to keep it down to one pipe?