Howard Harris
Member
In a Class II, Division 1 location, I can install two rigid conduits, vertically down, one conduit to a 120V device, one conduit to a 4-20ma device, liquidtight from each conduit to each device, with no sealoffs, just ductseal the end of each liquidtight in each device enclosure. Is this correct per NEC? Or does this mean to use sealoffs and seal with ductseal instead of Chico? Please explain.