i have a T building that needs 3- 200a panels feed. I have a existing H frame service with no load. The H frame sits about 150' away from T-building. The feeder needs to be ran overhead to New H frame that will feed New T building. I wanted to run 3- 200a disconnects from existing
H frame to each 200a panels but 225.30 doesn't allow me to run multiple feeders to T building. can I install 600a disconnect existing H frame with feeder then put Gutter at New H frame to feed the 3-200a panels . any ideas?

BTW just a theory 225.30 doesn't allow separate feeders only in special permissions 225.30 ( E ) if post a permanent plague like in 223.37 looks like i can get away with it. what you guys think?
 