This section is driving engineers crazy when it comes to generator sets. They believe it means that if you have multiple breakers on the genset, they have to be in different sections of a switchboard if different priorities - not unit mounted. Talked to NFPA (Who wont put it in writing) and that is NOT what they mean - they want emergency separated from legally required standby, etc.AT THE SWITCHGEAR
Has anyone seen anything clarifying this that we can get our hands on from ANYONE?