George#9
New member
- Location
- Santa Clara County
An installation is tapping after the meter before the main disconnect for a PV POC at a 277/480 main service. By definition is this a PV system disconnect or a service disconnect?, is a grounded conductor required (250.24C) from the tap to the disconnect in question.