Hello all,
Trying to design a genset system for a client. Its a odd ball for me. We are trying to feed two buildings. Each with a separate service entrance. One single phase and one three phase. My plan is to have genset with two breakers which would feed two separate ATS(service rated). Is this okay to do, given the difference in phase?
Thanks in advance.
Trying to design a genset system for a client. Its a odd ball for me. We are trying to feed two buildings. Each with a separate service entrance. One single phase and one three phase. My plan is to have genset with two breakers which would feed two separate ATS(service rated). Is this okay to do, given the difference in phase?