Abandoned Conduit

Status
Not open for further replies.

KJLEADER

New member
There is an existing underground 3 phase feed to a dishwasher which is being relocated. I plan to removed the existing 3 phase feed back to the panel. My concern is how should I abandon the conduit. Do I fill it with concrete or just cap it below the floor?
 
Speaking from experience, the conduit should be capped and shown on a record drawing. There have been many times that I have gone back to a building (especially restaurants and hospitals) for a new project where I wish a conduit was still in place that had been demoed on a previous renovation.

IMO, if a conduit or raceway is in usable condition and is not in the way after being abandoned, it should be left.

I hate seeing a blanket requirement to "remove back to source" any unused conduit and wiring.

Roger
 