I am working as a project engineer on the construction of a new cement plant. I have an electrician who is working with me in the field and is responsible for all QA/QC tasks. The electrican is very detail oriented and comes up with some elaborate schemes for running conduit in various areas.
I tend to go with what he is saying due to the fact that he has much more expereince in the field in regards to conduit routing and having to do maintance work on various installations.
However alot of times the electrical contractor will disagree with the proposed condiut routing and argue that it is unessary and will cost more money therefore it is not thier responsibility to install it as requested. I am then the one who is stuck arguing the commercial issues as to weather or not the required installation is absolutely necessary.
My question is what responsibilty the contractor has in adhering to what the client wants in regards to conduit routing. The specs are very vauge and do not give a whole lot of detail on this issue.
What are others experiences with "contractors duty" vs. "clients preference" in regards to conduit routing?
What about conduit that has already been installed and then the client works up a punch list requiring the contractor to move, re-route, or add fitting to conduit?
What about the client asking for various junction boxes and pull boxes throughout the project to make maintance of areas easier in the future?
I tend to go with what he is saying due to the fact that he has much more expereince in the field in regards to conduit routing and having to do maintance work on various installations.
However alot of times the electrical contractor will disagree with the proposed condiut routing and argue that it is unessary and will cost more money therefore it is not thier responsibility to install it as requested. I am then the one who is stuck arguing the commercial issues as to weather or not the required installation is absolutely necessary.
My question is what responsibilty the contractor has in adhering to what the client wants in regards to conduit routing. The specs are very vauge and do not give a whole lot of detail on this issue.
What are others experiences with "contractors duty" vs. "clients preference" in regards to conduit routing?
What about conduit that has already been installed and then the client works up a punch list requiring the contractor to move, re-route, or add fitting to conduit?
What about the client asking for various junction boxes and pull boxes throughout the project to make maintance of areas easier in the future?