• We will be performing upgrades on the forums and server over the weekend. The forums may be unavailable multiple times for up to an hour each. Thank you for your patience and understanding as we work to make the forums even better.

Added Panel

Status
Not open for further replies.

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
Existing building with the service etc. all existing. Adding one new panel being fed from a breaker in another panel.
Would this separate raceway and GEC be required run back to service switchboard as shown in attached?
 

Attachments

  • Screenshot 2023-01-27 104523.jpg
    Screenshot 2023-01-27 104523.jpg
    239.6 KB · Views: 19

augie47

Moderator
Staff member
Location
Tennessee
Occupation
State Electrical Inspector (Retired)
What do you mean shown with the feeder? It looks like a separate conduit with only a GEC from the panel to the service.
IF the new panel is being fed from the existing panel and they both in the same building you only need a properly sized feeder to the new panel with an EGC complying with 250.122, 250.118
No GEC is required.
(The #8 would be correct for an EGC on a 100 amp feeder but not required if the feeder raceway meets 250.118)
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
Everyone agrees the GEC is not required but it is permitted to run a GEC from the panel as shown in the drawing.
 
Last edited:
Status
Not open for further replies.
Top