Hello Every One:
I'm working on a small building where it's powered from a utility 150KVA (4160- 208Y/120V) pad mounted transformer. The Transformer secondary service conductor is owned by the utility Co and it terminate into a can labeled MLO and feeds a five meters via none-fused disconnect switches a head of each meter. Each meter feeds a panelboard (w/MCB) inside the building (total five panelboards - one for each tenant). The client has requested to add a generator to backup the entire building. My first thought was to intercept the secondary feeder and provide a service rated automatic transfer switch (ATS) near the utility transformer and also located the generator near the transformer as well. The challenge is, the secondary line is owned by the utility and not sure if they will let me intercept their line to add the ATS but I already contacted the utility and will wait on their response. My questions:
1. The ATS needs to be service rated and 4-poles, correct?
2. Can I use non-service rated ATS and leave everything as is as far the grounding and bonding of the service at the meters cans at the building? Or I have to have a disconnect a head of the ATS?
3. Is there better way doing it than what I describe above?
Your help is really appreciated
I'm working on a small building where it's powered from a utility 150KVA (4160- 208Y/120V) pad mounted transformer. The Transformer secondary service conductor is owned by the utility Co and it terminate into a can labeled MLO and feeds a five meters via none-fused disconnect switches a head of each meter. Each meter feeds a panelboard (w/MCB) inside the building (total five panelboards - one for each tenant). The client has requested to add a generator to backup the entire building. My first thought was to intercept the secondary feeder and provide a service rated automatic transfer switch (ATS) near the utility transformer and also located the generator near the transformer as well. The challenge is, the secondary line is owned by the utility and not sure if they will let me intercept their line to add the ATS but I already contacted the utility and will wait on their response. My questions:
1. The ATS needs to be service rated and 4-poles, correct?
2. Can I use non-service rated ATS and leave everything as is as far the grounding and bonding of the service at the meters cans at the building? Or I have to have a disconnect a head of the ATS?
3. Is there better way doing it than what I describe above?
Your help is really appreciated