Bill Marino
Member
- Location
- West Haven Ct.
I have an existing 600A-480/277V panel. From the 600A feeder breaker two sets of 500Kcmil feed an ATS(600A), and from there terminate on the main lugs of the above mentioned panel. There are spare lugs in the panel and I want to use them(tap off) to feed an additional panel so that existing equipment will have power supplied by the ATS during a power failure. There are no spare spaces in the 600A panel. There is 1-125 3 pole CB.(load XF 112.5), 2-100A 3 pole CB.(load Dist. PNL), 1-225A 3 pole CB.(load Dist. PNL), and 2-200A 3 pole CB.(load 2 Elevators) . The existing panels I want to add are 100A and 200A. They feed varied loads, one is for a sewage ejector pump system.
My question is how can I determine what my total load will be? I plan on taking actual current readings on all the panels.
I figure that I can use the actual current readings to determine the size of the main in the new panel, and if I'll be exceeding the current 600A ocpd. 125% of cont. plus 100% of non-cont.
Will it be a violation for me to use the spare lugs for the additional panel(taps)? I was reading Art. 240 on tap rules. The two panels(600A and new one) would be with in 10-15ft of each other, I plan on using a main breaker, and the tap conductors would be sized to the main.
Also this is a Hospital, (VA) are there any special considerations here as well?
Any help would be great.
My question is how can I determine what my total load will be? I plan on taking actual current readings on all the panels.
I figure that I can use the actual current readings to determine the size of the main in the new panel, and if I'll be exceeding the current 600A ocpd. 125% of cont. plus 100% of non-cont.
Will it be a violation for me to use the spare lugs for the additional panel(taps)? I was reading Art. 240 on tap rules. The two panels(600A and new one) would be with in 10-15ft of each other, I plan on using a main breaker, and the tap conductors would be sized to the main.
Also this is a Hospital, (VA) are there any special considerations here as well?
Any help would be great.