EmpireWind
Member
- Location
- Virginia
- Occupation
- Electrical Engineer
Reading through the NESC code section Part 4, working around energized and de-energized equipment in the switchyard, one of the precautions for approach especially voltages above 72.5kV, the control measure is to include blocking reclosing, prohibiting switching during live line work, using protective air gaps etc.
So in switchyards that are open to air, there is a disconnect switch along with a ground switch on both sides of the 52 breaker. My questions are as follows:
1. Is this more of a best practice or is this based on the interpretation of OSHA 1910.269 and NESC?
2. In the event of a gas insulated switch-gear how is the air-gap requirement satisfied as outlined in Table 441 1 through 4.
3. Does the disconnect switch and ground switch inside the GIS enclosure satisfy the air-gap requirement or is a separate disconnect switch outside the GIS needed to meet the air-gap requirements?
Would appreciate your feedback.
So in switchyards that are open to air, there is a disconnect switch along with a ground switch on both sides of the 52 breaker. My questions are as follows:
1. Is this more of a best practice or is this based on the interpretation of OSHA 1910.269 and NESC?
2. In the event of a gas insulated switch-gear how is the air-gap requirement satisfied as outlined in Table 441 1 through 4.
3. Does the disconnect switch and ground switch inside the GIS enclosure satisfy the air-gap requirement or is a separate disconnect switch outside the GIS needed to meet the air-gap requirements?
Would appreciate your feedback.