charlietuna
Senior Member
A friend is having a house built and asked me to look it over??? 200 amp panel fed by Aluminum Entrance Cable. Phase legs and neutral are properly terminated under the panel's lugs, but the service bond wire within the Service Entrance Cable(which is reduced in size from the manufacturer) has had three strands cut off in what looks like the installer had problems getting the bond into the bond bus lug. My question is: isn't this Service Entrance Cable's bond wire sized per the code???