It is a stupid question. It kinda bother me.
For example, when we do the load calculation for service, we said we need 1000A, it mean 1000A per phase.
But utility company ruling said "The service take-off(s) are each limited to 400 amperes
per phase per half hour demand and the entire vault installation is not to exceed 400 amperes per phase per
half hour demand."
The "400 amperes per phase per half hour demand" is kinda bother me. Does it mean 800A per phase per hour? so does utility only provide max 800A? or 400A?
(I made up the number, just want to bring up an example.)
For example, when we do the load calculation for service, we said we need 1000A, it mean 1000A per phase.
But utility company ruling said "The service take-off(s) are each limited to 400 amperes
per phase per half hour demand and the entire vault installation is not to exceed 400 amperes per phase per
half hour demand."
The "400 amperes per phase per half hour demand" is kinda bother me. Does it mean 800A per phase per hour? so does utility only provide max 800A? or 400A?
(I made up the number, just want to bring up an example.)