Anyone experiencing Eaton delays?

brantmacga

Senior Member
Location
Georgia
Occupation
Electrical contractor
Thought i should put this out there for anyone quoting Eaton right now.

I ordered a small gear package first week of April; two 225a panelboards, one 400a panelboard, and an 800A MDP.

They show my interior shipping mid June and the cans shipping last week of June. My supplier has the cans in stock, now hoping they can piece together the interiors from shelf stock.

When the PO was released I was told to expect normal shipping time of 4 weeks.

Yesterday I went looking for a CH 20/1 AFCI; none of the Eaton distributors here have any in stock, and I was told lots of breakers on back order.




Sent from my iPhone using Tapatalk
 

masterinbama

Senior Member
Needed 10 QO120's. Went to Graybar and was told 10 to 14 days. Luckily I had used in stock. Had to tell the customer I would have to come back and swap for new when they came in.

Sent from my LML211BL using Tapatalk
 

kwired

Electron manager
Location
NE Nebraska
If they shut down production and/or distribution warehouses then there could be impact to what was normal availability.

Shipping companies could end up creating delays as well.
 

brantmacga

Senior Member
Location
Georgia
Occupation
Electrical contractor
I expected this to happen, but to tell me there are no delays and then find out there is a 10 week delay is going to put me in a hard spot with the GC.


Sent from my iPhone using Tapatalk
 

Microwatt

Senior Member
Location
North Dakota
I put a $205k+ gear order in to Eaton about a year ago. Everything has been coming in as expected. Even the 5kv to 480v xfmr. They wrote a couple weeks ago that they were having trouble getting the surge arrestors for the 5kv MV switch and the ship date might push 4 weeks. Not a big deal now that the project has been shut down for the time being.
 

brantmacga

Senior Member
Location
Georgia
Occupation
Electrical contractor
Spoke with Eaton today. The main factory is closed, and will be closed for another 2 weeks at minimum.

They are having a satellite plant in Atlanta build out my panelboards for me which will get it here 2 weeks earlier.

Placed a Square D order this week, 60 day lead time now. Job will be done before the gear gets here.


Sent from my iPhone using Tapatalk
 

kwired

Electron manager
Location
NE Nebraska
Spoke with Eaton today. The main factory is closed, and will be closed for another 2 weeks at minimum.

They are having a satellite plant in Atlanta build out my panelboards for me which will get it here 2 weeks earlier.

Placed a Square D order this week, 60 day lead time now. Job will be done before the gear gets here.


Sent from my iPhone using Tapatalk
Was Square D order for factory assembled items or normally stocked items?

I may have a few panelboards and some pump panels to order coming up, but should be items that are typically stocked in their distribution system.
 

brantmacga

Senior Member
Location
Georgia
Occupation
Electrical contractor
Was Square D order for factory assembled items or normally stocked items?

I may have a few panelboards and some pump panels to order coming up, but should be items that are typically stocked in their distribution system.
It was a few 225A panelboards with breakers factory installed. And an 800 distribution panel.

The distributors I use normally stock these items also and can deliver to us unassembled if needed, but the problem is that normal stock has been exhausted across multiple brands due to factory closures.


Sent from my iPhone using Tapatalk
 

cwalkercomo

Member
Location
Columbia, MO
We're a Square D house and we've seen some massive backorders that have only gotten worse. Homeline 2 pole breakers are about 100,000-175,000 on back order. The other problem is that their system can't accurately tell us when we're expected to receive some of our orders, they say it's expected to ship 5/1 but we're in June now and there's no update. Square D had their distribution centers well stocked and maintaining orders for months but now their out and the factories themselves were either closed or running at low capacity. I would figure Eaton and the other brands are in the same boat as well right now.
 

Barbqranch

Senior Member
Location
Arcata, CA
Occupation
Plant maintenance electrician
I need a BJ3150 breaker to finish a compressor install. I was told they have 129 on back order. Yesterday I was able to buy a new one from eBay, should be shipped today.
 

Bob_Sacamano

Member
Location
Traverse City, MI
Occupation
electrician
My area is very understocked of all breakers from all brands. Eaton especially. I had to show my face in overpriced Ace Hardware just to get what I needed. Thankfully no one else shops there!
 