Jerseydaze
Senior Member
Im looking at there field guide for a 200 amp single phase resi mast And am confused it say on page 17 "? Three and one-half (3.5) feet between service drop conductors and roofs of projections not accessible to pedestrians." Then on page 44 it says referring to roof clearances If 30" or less use minimum of 2"steel conduit ,if more then 30" use 3" steel conduit.
OK so if I always need 42" from roof then I will always need 3" pipe wich I know not to be true I'm confused anyone help