jrannis
Senior Member
- Location
- Fort Lauderdale/ Miami
Gents,
I need some help defending this circa 1951 installation.
The 12 unit complex is two story.
Each of the first floor apartments has a 60 amp main lug fuse panel with both its feeder and the feeder for the apartment above it in the same conduit.
The feeder for the apartment on the second floor is looped through the panel on the first floor.
Is this installation still compliant? We are under the 2011 NEC?
The President of the condo association insists that the unit owners have been allowed by the City to repull new feeders and keep both feeders in the same conduit.
This doesn't seen correct to me but they insist it has been allowed as past practice.
Also,
The owner of the unit will require a 100 amp upgrade and will need to have a separate meter and main installed in te existing electric room as the existing meter center only has 60 amp fuse pull outs.
I will have to cut the feeder to the apartment above in order to change the fuse panel to a circuit breaker load center.
The inspector will accept us splicing the feeder to the above apartment if we enclose them in a separate junction with a tamper proof cover.
I believe that is his call and do not dispute this.
Much tanks for any inside you can provide
I need some help defending this circa 1951 installation.
The 12 unit complex is two story.
Each of the first floor apartments has a 60 amp main lug fuse panel with both its feeder and the feeder for the apartment above it in the same conduit.
The feeder for the apartment on the second floor is looped through the panel on the first floor.
Is this installation still compliant? We are under the 2011 NEC?
The President of the condo association insists that the unit owners have been allowed by the City to repull new feeders and keep both feeders in the same conduit.
This doesn't seen correct to me but they insist it has been allowed as past practice.
Also,
The owner of the unit will require a 100 amp upgrade and will need to have a separate meter and main installed in te existing electric room as the existing meter center only has 60 amp fuse pull outs.
I will have to cut the feeder to the apartment above in order to change the fuse panel to a circuit breaker load center.
The inspector will accept us splicing the feeder to the above apartment if we enclose them in a separate junction with a tamper proof cover.
I believe that is his call and do not dispute this.
Much tanks for any inside you can provide