mrktaylor7
Member
- Location
- Hawaii
- Occupation
- Urban planner
Hi everyone, I could use some help.
1. Is it possible to review a 46kV substation under the NEC but the substation was designed to meet NESC?
2. Why or why not? Are there safety hazards created?
This is a real situation. A PV facility is constructing a substation for a local utility, however, since the substation is not being constructed directly by the utility, the code exemption to the NEC is not applicable. A building permit needs to be submitted and the substation will need to meet the NEC.
1. Is it possible to review a 46kV substation under the NEC but the substation was designed to meet NESC?
2. Why or why not? Are there safety hazards created?
This is a real situation. A PV facility is constructing a substation for a local utility, however, since the substation is not being constructed directly by the utility, the code exemption to the NEC is not applicable. A building permit needs to be submitted and the substation will need to meet the NEC.