JimCrowell
Member
Hi.
I've searched the forums and cannot find this question addressed clear enough for several persons involved in the evaluations and decision making, hope you can help.
We're looking for guidance or discussion for arc flash hazards when changing fuses in fused switches in a switchboard. The switchboard is energized, the fused switch is in the off position, the switchboard is energized. One group is claiming the fused switch does not have energized components present or otherwise provides a reduction in hazard below that of OCPD supplying power to the supply side of the fused switch. Another group claims that since the line side of the switch is energized the arc flash hazard is that of the supply to the switch.
Other information that seems important - 1) the fused switch is not locked out, 2) voltage measurements to verify the fuses at the supply side would have the incident energy rating of the OCPD supplying the switch, 3) the fused switch compartment has the supply connectors energized, and 4) the arc flash PPE requirements are based on the severity and not the relative likelyhood of an arc flash occuring.
Thanks in advance,
Jim Crowell
I've searched the forums and cannot find this question addressed clear enough for several persons involved in the evaluations and decision making, hope you can help.
We're looking for guidance or discussion for arc flash hazards when changing fuses in fused switches in a switchboard. The switchboard is energized, the fused switch is in the off position, the switchboard is energized. One group is claiming the fused switch does not have energized components present or otherwise provides a reduction in hazard below that of OCPD supplying power to the supply side of the fused switch. Another group claims that since the line side of the switch is energized the arc flash hazard is that of the supply to the switch.
Other information that seems important - 1) the fused switch is not locked out, 2) voltage measurements to verify the fuses at the supply side would have the incident energy rating of the OCPD supplying the switch, 3) the fused switch compartment has the supply connectors energized, and 4) the arc flash PPE requirements are based on the severity and not the relative likelyhood of an arc flash occuring.
Thanks in advance,
Jim Crowell