Hello Everyone:
Does the NEC require us to perform an Arc Flash Study for the entire facility if a an existing generator (1000KW) is being replaced by larger one (2000KW)? There are additional mechanical loads are being added to the new generator. We will need to add another main breaker to the main service switchboard to accommodate this change. New equipment such as ATS's/switchboard/dist panels will be added. My thought since the main service source (utility transformer) is not being changed, which delivers the worst fault current, we only required to do the arc flash study for the new equipment added.
Any thoughts?
Thanks,
Does the NEC require us to perform an Arc Flash Study for the entire facility if a an existing generator (1000KW) is being replaced by larger one (2000KW)? There are additional mechanical loads are being added to the new generator. We will need to add another main breaker to the main service switchboard to accommodate this change. New equipment such as ATS's/switchboard/dist panels will be added. My thought since the main service source (utility transformer) is not being changed, which delivers the worst fault current, we only required to do the arc flash study for the new equipment added.
Any thoughts?
Thanks,