Sparky2791
Senior Member
- Location
- Northeast, PA
- Occupation
- Electrical Design
Hello - We designed a 12470V electrical distribution for a waste water treatment campus and the EC sent in this RFI (attached) regarding the MV Feeder conductors based on a section in the specifications.
Never had this question asked before as I always figured each cable wrapped independently mostly because the portions of the circuit that need to be wrapped are separated where the terminations to the equipment are required and could not be wrapped together. Any thoughts as to why they would ask this question? Kind of puzzling to me. Thanks for looking/responding!
Never had this question asked before as I always figured each cable wrapped independently mostly because the portions of the circuit that need to be wrapped are separated where the terminations to the equipment are required and could not be wrapped together. Any thoughts as to why they would ask this question? Kind of puzzling to me. Thanks for looking/responding!