I need a clarification.
I'm feeding a 30kva transformer from a 277/480 volt panel. then the transformer will feed a 120/208 panel.
This system is piped together using EMT, changeover and Flex Metal conduit on both sides (Primary/Secondary).
I've always been under the impression that on the secondary side of the transformer (120/208 volt), before the overcurrent protection. I was required to use BONDING/GROUNDING BUSHINGS and run my grounded conductor through them. This 120/208 would be a New Service from a separately derived system.
Thank You, Joe Miki
I'm feeding a 30kva transformer from a 277/480 volt panel. then the transformer will feed a 120/208 panel.
This system is piped together using EMT, changeover and Flex Metal conduit on both sides (Primary/Secondary).
I've always been under the impression that on the secondary side of the transformer (120/208 volt), before the overcurrent protection. I was required to use BONDING/GROUNDING BUSHINGS and run my grounded conductor through them. This 120/208 would be a New Service from a separately derived system.
Thank You, Joe Miki