Can someone help clarify a VRU setup for Natural gas processing and reclaiming Vapors off of our dumps from the plant. We have a new tank farm and have installed a VRU skid mounted unit. The VRU unit is rated as a class 1 Div 2 . How far away from tanks and or the containment wall must the unit be installed to be able to operate the VRU unit. The system will operate between 4 ounces and 8 ounces. The potential for release would be either the 150 series flange within 2 feet of the VRU skid or possibly the thief hatches on the tanks themselves spilling into the containment area. The tank farm is moved away from the plant processing area by more than 300 feet. My thoughts were that we should be at minimum of 50 feet before using Class 1 Div 2 otherwise if it is close to the tanks or a possible release we should have Class 1 Div 1 equipment.
Thank you
Thank you