Kyle S. Budd Jr.
Member
- Location
- Corpus Christi, Texas
The question I have is were does the tap occur? Conditions 1, 2, and 3 of article 240.21.2 are met in this installation. We have an installation in a single family dwelling where there is a 400 amp main breaker transfer switch rated for service equipment that the taps supplies power to two 200 amp 120/240 volt single phase main breaker panels. The load side lugs of the transfer switch are a double barrel lug. We connected each tap conduct from the transfer switch load lug and terminated them to the main breaker in each panel. The transfer switch line lugs are fed from the utility meter with parallel 2/0. Our Authority is interpreting that we have to run 400 amp conductors or parallel 2/0 off the load lugs before we can make the tap with an approved lug or other connection. What is your thought on this?
Kyle S. Budd Jr.
Budd Electric Co. Inc.
Kyle S. Budd Jr.
Budd Electric Co. Inc.