Dale001289
Senior Member
- Location
- Georgia
Construction is pulling TC-ER, 600V, multi-conductor cable to low-voltage loads, typically via cable tray to PVC conduit underground ductbank with very little above grade, rigid-metal conduit utilized.
Two scenarios:
· Scenario 1: Cables enter the duct bank system off cable tray ‘water-falls’ from a piperack in a non-hazardous area. They route underground to Division 2 areas where they stub-up for motors and their associated control stations.
In Division 2, they're installing conduit boundary seals and routing ‘free-air’ to the motor termination box where they connect using Crouse-Hinds TMCX connectors.
At the non-hazardous side, whereit enters the duct bank, there is no conduit boundary seal at the stub-up.
· Scenario 2: Exactly like scenario 1 except both ends stub-up in Division 2 area, yet neither end has conduit boundary seals.
Are either of these scenarios a violation of 501.15(B)(2)?
Two scenarios:
· Scenario 1: Cables enter the duct bank system off cable tray ‘water-falls’ from a piperack in a non-hazardous area. They route underground to Division 2 areas where they stub-up for motors and their associated control stations.
In Division 2, they're installing conduit boundary seals and routing ‘free-air’ to the motor termination box where they connect using Crouse-Hinds TMCX connectors.
At the non-hazardous side, whereit enters the duct bank, there is no conduit boundary seal at the stub-up.
· Scenario 2: Exactly like scenario 1 except both ends stub-up in Division 2 area, yet neither end has conduit boundary seals.
Are either of these scenarios a violation of 501.15(B)(2)?