Construction needs 480V temporary construction power. They want 3-100A three phase feeders to a new unit under construction. An existing MCC contains the required circuit breakers, but the upstream 1000kVA power transformer that feeds the MCC main circuit breaker is out of service. Construction wants to 'back-feed 'the MCC via a 400A branch circuit breaker in one of the vertical sections from another nearby power transformer secondary that is lightly loaded. Is this permissible for temporary power under NEC?