cvirgil467
Senior Member
- Location
- NewYork
Having a problem interpreting 700-10-D(1) in the 2011 edition which relates to where 2 hr wiring is required. Shafts and spaces above hung ceiling are not typicaly sprinklered and where the majority of feeders and branch circuits are installed. Starting from this base that emergency feeders are routed above ceiling and in shafts that are not sprinklered, I have the following question:
1. Does the 2 hr requirement for the feeder from the generator to the first ATS or first emergency distribution board or is it the entire wiring distribution from generator down to the branch circuit wiring to light fixtures, outlets, etc.
Thanks.
c
1. Does the 2 hr requirement for the feeder from the generator to the first ATS or first emergency distribution board or is it the entire wiring distribution from generator down to the branch circuit wiring to light fixtures, outlets, etc.
Thanks.
c