Recently had a job inspected and it passed! In short the job was to convert old pneumatics control of multiple hvac units to ddc in a fairly big facility. I saw some things that I didn’t think would pass, pass. To make a long story short wires were strung across the ceiling grid and supported to the duct work all over the place with tie wraps and holes were drilled thru block walls and cables were pulled thru them (without sleeves). Some with fire caulk in them and some just pulled thru the drilled out holes (some of these penetrations may not have been firewalls so maybe that’s why they didn’t have fire caulk.. Job was not done in a neat and workman like manner. Oh and cables were taped to threaded rod. The only thing called out was some of the wiring laying on the grid which is spelled out pretty clear in 725. But anyways after digging through article 725 it seems like 725.3 throws out everything thing in article 300 and just references it here and there such as 300.4(d) and 300.22 and it does not clarify any of these issues for me. Basically what im getting out of this article is if it doesn’t say you cant do it, you can and as far as supporting you just need to support your cable to the structure with a listed strap etc referred in 725.24. All wire was plenum rated.
1. So I guess my question is can you straps cables to duct work some not so long and some for long stretches?
2. Can you run cables thru block walls without sleeves?
3. Can you tape cables to threaded rod?
4. Can you tie class 2 and 3 cables to ceiling grid wire (not independent wires)?It doesn’t say you can’t in 725
I guess I wouldn’t have done some of the things they did but it seems to me that other than laying wires on the grid somewhere there job was code I guess because not only did the inspector pass it but I cant find anything in the code saying anything they did was wrong. Looking for some opinions Thanks
1. So I guess my question is can you straps cables to duct work some not so long and some for long stretches?
2. Can you run cables thru block walls without sleeves?
3. Can you tape cables to threaded rod?
4. Can you tie class 2 and 3 cables to ceiling grid wire (not independent wires)?It doesn’t say you can’t in 725
I guess I wouldn’t have done some of the things they did but it seems to me that other than laying wires on the grid somewhere there job was code I guess because not only did the inspector pass it but I cant find anything in the code saying anything they did was wrong. Looking for some opinions Thanks