electrofelon
Senior Member
- Location
- Cherry Valley NY, Seattle, WA
I have done quite a few generators over the years, dozens probably, mostly generac or Kohler. All of the Kohler have been RXT series where the ATS is proprietary with the generator controller. So anyway I have a 150KW Kohler and a Thompson 600A ATS that I am getting close to commissioning. So these are just standard 2 wire start, which I have actually never actually worked with. So am I missing anything or do I just need 2 wires between the ATS and then gen? Are they typically any other wires between the two? Do I just run like 2 #12 THHN for this? Does the ATS just transfer based on where it senses an acceptable power source (subject to whatever timing and delays are programmed in the ATS)? I know I need 120v power for accessories which in this case is just a battery charger. Yes I do have all the paperwork but its like 437 pages and I havent been able to even find the basic info yet., just wanted to tough base on the forum here first.
Second question: The logistics of this job are tricky as it is an operational facility and it is super hard to get a shutdown. I need to temp power stuff on the load side of the ATS by feeding the generator side of the ATS with a temp feeder. I can manually transfer it over or just let it transfer when it senses power on the gen terminals, but anything else I should know?
I know I do need to change the voltage configuration of the ATS. It came from the factory set at 480, but this is 208.
Second question: The logistics of this job are tricky as it is an operational facility and it is super hard to get a shutdown. I need to temp power stuff on the load side of the ATS by feeding the generator side of the ATS with a temp feeder. I can manually transfer it over or just let it transfer when it senses power on the gen terminals, but anything else I should know?
I know I do need to change the voltage configuration of the ATS. It came from the factory set at 480, but this is 208.