Hello all,
When I put the auxiliary rod at a pad mount, I always bring the #6 bare back in the ditch and irreversible it at the main GEC. Recently, I went and looked at an install where they ran a #6 thwn from the combiner at the pad through the pvc and then landed the other end in the MDP on the ground bar. They did drive a rod at the pad and split bolted the bare from the rod to the #6 thwn-2 in the combiner box and then sent it on. Is this legal to be done this way?
When I put the auxiliary rod at a pad mount, I always bring the #6 bare back in the ditch and irreversible it at the main GEC. Recently, I went and looked at an install where they ran a #6 thwn from the combiner at the pad through the pvc and then landed the other end in the MDP on the ground bar. They did drive a rod at the pad and split bolted the bare from the rod to the #6 thwn-2 in the combiner box and then sent it on. Is this legal to be done this way?